Field Studies

NORTH of the ARCTIC CIRCLE

 

THAT OLD EXPRESSION "breaking new ground" is not just an expression--or at least, not in Inuvik, Northwest Territories, Canada. That is where they are building the first below-ground pipeline north of the Arctic Circle in Canada--and "breaking new ground" is exactly what they are doing during this grueling wintertime project. It is a challenging project--one that combines severe cold, isolation, and frozen tundra.
"This kind of digging is tough," said Shawn Reid, president of Reid's Pipeline, Ltd., the contracting company from Cold Lake, Alberta that tackled the job. "But this kind of digging probably represents the new frontier for gas and oil development. Some of the biggest gas and oil deposits in Canada are located just north of where we're working. And somehow, it all has to come south."

Inuvik is located about 160 miles (258 km) north of the Arctic Circle. The Inuvik Gas Project that Reid's Pipeline is working on will collect natural gas from two wells located about 30 miles (50 km) north of Inuvik and bring it to the city's power-generation plant. 
  
"The intent of this project is to convert the current diesel-powered generation system in Inuvik to natural gas," Reid explained. "That's mainly because it's so expensive to get the diesel fuel up here. They have to haul it by road all the way from Edmonton, which is about a 40-hour, one-way trip with a truck."

The trenching part of the project involves cutting through permafrost for the length of the pipeline. 

"The first half of the pipeline project," said Reid, "was covered with short trees and was generally clay material. But once we passed the midway point, we were into wide-open tundra." 

Reid's crew is using a new Trencor 1260HD chain trencher to do most of the trenching. 

"This is our first experience with this kind of trencher," Reid said. "We bought it specifically for this job. Before owning the Trencor, we were using mostly track excavators for our ditching operations. But in digging conditions like we have in Inuvik, the Trencor will do the work of three or four track excavators."

The entire project is being done in the middle of the winter, Reid explained. The company's crews started trenching around the beginning of January and they planned to be finished by the end of March. 

"Nothing stops us," said Reid. "Absolutely nothing. It has been as cold as -58° F (-50° C) and that trencher just keeps trudging along. We never shut it down, especially during those extreme temperatures." 

As one might imagine, the job performance of a trencher under such conditions depends largely on what kind of soil is being cut. "Basically, we're cutting a trench that is 15 in. (38 cm) wide and 6 ft. (1.8 m) deep. When we're in good clay material, we will get anywhere from 9 to 14 ft. per minute (2.7 to 4.3 m) with the Trencor trencher.

"But there are some areas where we will run into really bad, rocky conditions: big, round granite boulders scattered here and there. Glacial deposits. We don't even try to cut through those things. Instead, we pull the trencher out and bring in a track excavator to rip them out of the ground." 

Reid said the crew was averaging about 0.6 mile (1 km) per day over the course of the entire project. The quality of the trench and the quality of the spoil material was also something that Reid singled out for favorable comment.

"Compared to what a track excavator can do," Reid said, "this machine leaves a much nicer trench. It is much neater and cleaner. And it is more environmentally friendly, too--mainly because we disturb a lot less soil when we are digging with our trencher. 

"With the Trencor chain trencher, we can dig a ditch that is only about 14 or 15 in. (36 or 38 cm) wide. But if we used a track excavator, the bucket is about 30 in. (76 cm) wide--so we'd be tearing up twice as much ground." 

Reid said he and his crew are very satisfied with their Trencor 1260HD trencher and the job it has been doing for his company. 

"One thing is for sure," Reid said. "The trencher definitely speeds up the back end of a pipeline job. It greatly reduces the backfilling and the clean-up that is normally so time- and labor-intensive." 

And what would he tell another contractor who was thinking about getting a Trencor trencher? 

"It seems like a well-built machine. And I've been happy with the service we've been getting from Trencor. The people down there are more than helpful.

"Time will tell. But I think we've made a good investment."

Please contact Astec Underground at
9600 Corporate Park Drive | Loudon, TN 37774-5584
Phone (865) 408-2100 | Toll Free (800) 527-6020 | Fax (865) 458-8575

© 2001-2005 Astec Industries, Inc. All Rights Reserved. Legal Notice | Privacy Policy | Webmaster | Site Map